How to Review a Bitumen Storage Tank Layout Before Ordering

FEITENG

Cover photo: a FEITENG YZSL horizontal bitumen storage tank with visible end connections.

Before approving a bitumen storage tank order, ask for a general arrangement drawing (GA) and compare it with your site plan. Check where the tank will sit, how people will reach it, where the pipes will connect and which work each party will supply. Record open items against the drawing revision so they can be resolved before fabrication.

1. Check the footprint and the space around it

Ask the supplier to identify the overall envelope, including platforms, ladders and projecting connections. Mark it on the site plan with a fixed reference point. Walk through the delivery route, final installation position and maintenance access with the site team. A drawing can fit inside a plot boundary while still leaving insufficient room to remove a pump, open an access cover or approach an instrument.

2. Match each connection to the site pipework

Compare the drawing and nozzle schedule with the site's piping plan. For each connection, confirm its service, location, orientation, elevation and interface specification. Pay particular attention to which end of the tank faces the pump area. If a connection moves between revisions, ask the piping team to check the effect on the route and access before approving the change.

Illustration based on a FEITENG YZSL horizontal bitumen tank showing the end piping and valves
Illustration based on a FEITENG YZSL tank photo. Use the approved project drawing to confirm connection positions and dimensions.

3. Agree where the supplier's scope ends

Mark the physical connection points for the tank, heating equipment, pumps and controls. Put an owner beside foundations, lifting, external piping, field wiring and commissioning. Ask for the project-specific foundation loads, support details and installation documents needed by the responsible engineers. Confirm any item shown for reference only against the written quotation before including it in the purchase scope.

Drawing review checklist

Review item What to mark on the drawing Evidence to request
Placement and access Tank orientation, reference point, access routes and service zones Dimensioned arrangement and current site plan
Pipe connections Nozzle tags, direction, elevation and connection boundaries Nozzle schedule and matching piping plan
Foundations and installation Support locations, delivery route and site work boundary Approved support information and installation plan
Utilities and controls Heating connections, power and control interfaces Utility schedule and a written responsibility list
Approval Drawing number, revision, unresolved items and owners Written disposition and the approved drawing revision

4. Close open items before signing

Imagine that the tank outlet faces the opposite side from the planned pump. Record the affected nozzle tag, drawing revision and intended pipe route. Ask the supplier and site piping lead to agree whether to revise the arrangement or revise the site plan. Keep the agreed decision with the order documents so the two teams work from the same layout.

Before placing the order, send your site plan, target working capacity, operating requirements and existing connection details for a configuration review. Browse the FEITENG bitumen storage tank range or send FEITENG your project details.